Earned Value and Cost Control
Navigation: phase-workflows | index
Earned Value Management (EVM) integrates scope, schedule, and cost to measure project performance and forecast outcomes. Once construction starts, the GMP estimate becomes the cost baseline (Budget at Completion), and EVM tells you whether you’re tracking to it.
The Three Core EVM Values
Section titled “The Three Core EVM Values”| Value | Acronym | Definition | How to Get It |
|---|---|---|---|
| Planned Value | PV | Budgeted cost for work scheduled by this date | % planned complete × BAC |
| Earned Value | EV | Budgeted cost for work actually accomplished | Actual % complete × BAC |
| Actual Cost | AC | What you actually spent to do the work done | Actual invoices, payroll, sub invoices paid |
The Six Key EVM Metrics
Section titled “The Six Key EVM Metrics”Cost Variance (CV)
Section titled “Cost Variance (CV)”CV = EV - ACCV > 0 = under budget | CV < 0 = over budget
Schedule Variance (SV)
Section titled “Schedule Variance (SV)”SV = EV - PVSV > 0 = ahead of schedule | SV < 0 = behind schedule
Cost Performance Index (CPI)
Section titled “Cost Performance Index (CPI)”CPI = EV / ACCPI > 1.0 = under budget | CPI < 1.0 = over budget
Critical rule: CPI tends to stabilize after the project is ~20% complete. A CPI of 0.90 at 25% complete typically predicts a CPI near 0.90 at completion — it does not self-correct without intervention.
Schedule Performance Index (SPI)
Section titled “Schedule Performance Index (SPI)”SPI = EV / PVSPI > 1.0 = ahead of schedule | SPI < 1.0 = behind schedule
Estimate at Completion (EAC)
Section titled “Estimate at Completion (EAC)”The most important forward-looking metric — your current best forecast of total project cost.
EAC = BAC / CPI [assumes current CPI continues]EAC = AC + (BAC - EV) / CPI_future [if you believe CPI will improve]EAC = AC + (BAC - EV) / (CPI × SPI) [if schedule is also driving cost]Estimate to Complete (ETC)
Section titled “Estimate to Complete (ETC)”ETC = EAC - ACTo-Complete Performance Index (TCPI)
Section titled “To-Complete Performance Index (TCPI)”What CPI you must achieve on remaining work to finish within budget:
TCPI = (BAC - EV) / (BAC - AC) [to finish within original BAC]TCPI = (BAC - EV) / (EAC - AC) [to finish within current EAC]TCPI > 1.2 = very unlikely to recover without scope reduction or additional funding.
Monthly Reporting Cycle
Section titled “Monthly Reporting Cycle”- Update the cost-loaded schedule — confirm PV, actual % complete, and AC for the period
- Calculate EVM metrics for the full project and by CSI division / work package
- Investigate root causes — which division has the biggest variance? Is it productivity, material cost, scope change, or measurement?
- Report to owner and take corrective action
Monthly cost report must include:
- EVM summary table (PV, EV, AC, CPI, SPI, EAC)
- Contingency tracking (original, approved draws, remaining balance)
- Change order log summary (approved, pending, total GMP revision)
- Forecast to complete narrative (what you plan to do differently)
- Risk log update
Worked Example: 35,000 SF Food & Bev Expansion — Month 4
Section titled “Worked Example: 35,000 SF Food & Bev Expansion — Month 4”| Metric | Value |
|---|---|
| BAC (GMP cost-of-work baseline) | $18,200,000 |
| PV (planned through Month 4) | $7,280,000 (40% planned) |
| EV (actual % complete × BAC) | $6,552,000 (36% complete) |
| AC (actual cost incurred) | $7,150,000 |
| CV | -$598,000 (over budget) |
| SV | -$728,000 (behind schedule) |
| CPI | 0.916 |
| SPI | 0.900 |
| EAC | $19,869,000 |
| ETC | $12,719,000 |
At current performance, the project will overrun cost-of-work baseline by ~$1.67M. Contingency must cover this gap or corrective action must reduce the overrun.
Contingency Tracking Integrated With EVM
Section titled “Contingency Tracking Integrated With EVM”| Month | EAC | BAC | Forecast Overrun | Contingency Remaining | Cushion |
|---|---|---|---|---|---|
| 1 | $18,200,000 | $18,200,000 | $0 | $2,184,000 | $2,184,000 |
| 2 | $18,450,000 | $18,200,000 | $250,000 | $2,050,000 | $1,800,000 |
| 3 | $18,700,000 | $18,200,000 | $500,000 | $1,900,000 | $1,400,000 |
| 4 | $19,869,000 | $18,200,000 | $1,669,000 | $1,600,000 | -$69,000 |
By Month 4, forecast overrun exceeds remaining contingency — triggers immediate escalation to PM and owner before the money is gone.
Advisor content
Continue reading with Advisor
This article is part of our Advisor library — written from real projects, not generic explainers.
- Full Support tier vault — equipment, integration, commissioning, takeoff, and more
- Practitioner-level guidance from real projects
- Unlimited AI questions across the Support corpus
$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime
Already subscribed? Sign in