Skip to content
Estimating

Earned Value and Cost Control

Navigation: phase-workflows | index

Earned Value Management (EVM) integrates scope, schedule, and cost to measure project performance and forecast outcomes. Once construction starts, the GMP estimate becomes the cost baseline (Budget at Completion), and EVM tells you whether you’re tracking to it.


ValueAcronymDefinitionHow to Get It
Planned ValuePVBudgeted cost for work scheduled by this date% planned complete × BAC
Earned ValueEVBudgeted cost for work actually accomplishedActual % complete × BAC
Actual CostACWhat you actually spent to do the work doneActual invoices, payroll, sub invoices paid

CV = EV - AC

CV > 0 = under budget | CV < 0 = over budget

SV = EV - PV

SV > 0 = ahead of schedule | SV < 0 = behind schedule

CPI = EV / AC

CPI > 1.0 = under budget | CPI < 1.0 = over budget

Critical rule: CPI tends to stabilize after the project is ~20% complete. A CPI of 0.90 at 25% complete typically predicts a CPI near 0.90 at completion — it does not self-correct without intervention.

SPI = EV / PV

SPI > 1.0 = ahead of schedule | SPI < 1.0 = behind schedule

The most important forward-looking metric — your current best forecast of total project cost.

EAC = BAC / CPI [assumes current CPI continues]
EAC = AC + (BAC - EV) / CPI_future [if you believe CPI will improve]
EAC = AC + (BAC - EV) / (CPI × SPI) [if schedule is also driving cost]
ETC = EAC - AC

What CPI you must achieve on remaining work to finish within budget:

TCPI = (BAC - EV) / (BAC - AC) [to finish within original BAC]
TCPI = (BAC - EV) / (EAC - AC) [to finish within current EAC]

TCPI > 1.2 = very unlikely to recover without scope reduction or additional funding.


  1. Update the cost-loaded schedule — confirm PV, actual % complete, and AC for the period
  2. Calculate EVM metrics for the full project and by CSI division / work package
  3. Investigate root causes — which division has the biggest variance? Is it productivity, material cost, scope change, or measurement?
  4. Report to owner and take corrective action

Monthly cost report must include:

  1. EVM summary table (PV, EV, AC, CPI, SPI, EAC)
  2. Contingency tracking (original, approved draws, remaining balance)
  3. Change order log summary (approved, pending, total GMP revision)
  4. Forecast to complete narrative (what you plan to do differently)
  5. Risk log update

Worked Example: 35,000 SF Food & Bev Expansion — Month 4

Section titled “Worked Example: 35,000 SF Food & Bev Expansion — Month 4”
MetricValue
BAC (GMP cost-of-work baseline)$18,200,000
PV (planned through Month 4)$7,280,000 (40% planned)
EV (actual % complete × BAC)$6,552,000 (36% complete)
AC (actual cost incurred)$7,150,000
CV-$598,000 (over budget)
SV-$728,000 (behind schedule)
CPI0.916
SPI0.900
EAC$19,869,000
ETC$12,719,000

At current performance, the project will overrun cost-of-work baseline by ~$1.67M. Contingency must cover this gap or corrective action must reduce the overrun.


MonthEACBACForecast OverrunContingency RemainingCushion
1$18,200,000$18,200,000$0$2,184,000$2,184,000
2$18,450,000$18,200,000$250,000$2,050,000$1,800,000
3$18,700,000$18,200,000$500,000$1,900,000$1,400,000
4$19,869,000$18,200,000$1,669,000$1,600,000-$69,000

By Month 4, forecast overrun exceeds remaining contingency — triggers immediate escalation to PM and owner before the money is gone.

Advisor content

Continue reading with Advisor

This article is part of our Advisor library — written from real projects, not generic explainers.

  • Full Support tier vault — equipment, integration, commissioning, takeoff, and more
  • Practitioner-level guidance from real projects
  • Unlimited AI questions across the Support corpus

$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime