BOE Template

Navigation: estimate-classification | index

Copy this template for every estimate you produce. Fill in every section. A blank section is not acceptable — if a section doesn’t apply, state why.


Project Name: _______________________________________________ Project Location: _______________________________________________ Owner/Client: _______________________________________________ Design-Build Contractor: _______________________________________________ Prepared By: _______________ | Date: _______________ Reviewed By: _______________ | Date: _______________ Estimate Revision: Rev ___ | Supersedes: Rev ___


FieldValue
AACE Estimate ClassClass ___ (1 / 2 / 3 / 4 / 5)
Expected Accuracy Range-% / +%
Design Completeness___%
Estimate PurposeROM / Feasibility / Budget Authorization / GMP Submission / Check Estimate
Pricing DateAll unit rates and quotes valid as of: _______________
LocationCity, State
Location Factor Applied___ (vs. national average = 1.00)

DocumentRevisionDateSource
Architectural Floor PlanRev ___//___A/E firm
Site / Civil PlanRev ___//___Civil engineer
Structural Framing PlanRev ___//___Structural engineer
Mechanical P&IDsRev ___//___Process engineer
Electrical SLDRev ___//___Electrical engineer
Equipment ListRev ___//___Owner / process engineer
Geotechnical ReportRev ___//___Geotech firm
SurveyRev ___//___Surveyor
SpecificationsRev ___//___A/E firm
Owner’s RFPRev ___//___Owner

Documents NOT available (assumed):



Building / Structural:

  • _______________________________________________

Civil / Site:

  • _______________________________________________

Mechanical / Plumbing:

  • _______________________________________________

Electrical:

  • _______________________________________________

Process Equipment (Divisions 40–45):

  • _______________________________________________

Soft Costs:

  • Design fees: $___________ (___% of construction cost)
  • Permits and fees: $___________
  • Testing and inspection: $___________

  • Owner-furnished equipment (OFE): All equipment on OFE list
  • Process equipment vendor startup and commissioning labor
  • IT infrastructure, MES/SCADA/PLC programming and software
  • Production validation (for food/pharma)
  • Furniture, fixtures, and equipment beyond scope drawings
  • Hazardous materials abatement (pending survey — see allowance in Section 8)
  • Escalation beyond pricing date (see Section 7)
  • _______________________________________________

Cost CategoryMethodSource
Site work / EarthworkBottom-up QTO from civil drawings; unit rates from RSMeansRSMeans, adjusted for [location]
ConcreteQTO from structural drawings; sub quoteSub quote + RSMeans check
Structural steelTonnage from framing plan; erect + supply sub quoteSub quote [Sub Name]
Roofing / envelopeQTO from architectural drawings; sub quoteSub quote [Sub Name]
Mechanical / plumbingPreliminary QTO; sub quotesSub quote [Sub Name(s)]
ElectricalLoad schedule + QTO; sub quotesSub quote [Sub Name(s)]
Fire suppressionSF-based parametric; sub quoteSub quote [Sub Name]
Process equipmentEquipment list + vendor budget quotes + Lang factor for installVendor quotes, Lang = ___
Process pipingP&ID count method; sub quoteSub quote [Sub Name]
General conditionsDetailed line item (see attached GC schedule)Project schedule + market rates

TradeSub NameQuote DateQuote AmountLeveled AmountNotes
Structural steel$$
Mechanical$$
Electrical$$
Roofing$$
Concrete$$
Fire suppression$$

ItemValue
Pricing date_______________
Estimated construction start_______________
Estimated construction midpoint_______________
Annual material escalation rate___% (source: ENR CCI / BLS PPI)
Annual labor escalation rate___% (source: prevailing wage / union CBA)
Total escalation $$ _______________
Escalation as % of base estimate___%

ItemValue
Contingency methodFlat % / Expected Value / Monte Carlo
Design development allowance$ _______________ (___% of base)
Scope gap allowance$ _______________ (___% of base)
Execution / risk contingency$ _______________ (___% of base)
Total contingency$ _______________
Total contingency as % of base____%
Confidence level (if Monte Carlo)P___

ItemAmountBasis
Hazardous materials (pending survey)$ _______________Allowance — prior similar projects
Permit fees$ _______________Jurisdiction fee schedule estimate
Owner’s testing and inspection$ _______________Historical $/SF
Utility connection fees$ _______________Utility company estimate

Cost ComponentAmount% of GMP
Direct Cost of Work$ __________________%
General Conditions$ __________________%
Design Fees$ __________________%
Escalation$ __________________%
Contingency$ __________________%
Contractor Fee (___%)$ __________________%
GMP TOTAL$ _______________100%

Section 11: Assumptions and Qualifications

Section titled “Section 11: Assumptions and Qualifications”
  1. Soil bearing capacity assumed at 2,000 PSF; if lower, deep foundations will add cost (not included).
  2. No hazardous materials in existing building assumed; abatement allowance of $_____ included.
  3. Estimate assumes current labor market conditions as of pricing date.
  4. Owner’s equipment (OFE) is delivered on schedule per project schedule. OFE delay is not contractor responsibility.

Advisor content

Continue reading with Advisor

This article is part of our Advisor library — written from real projects, not generic explainers.

  • Full Support tier vault — equipment, integration, commissioning, takeoff, and more
  • Practitioner-level guidance from real projects
  • Unlimited AI questions across the Support corpus

$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime