Change Order Management
Navigation: phase-workflows | index
A change order (CO) is a formal amendment to the GMP contract that modifies scope, cost, or schedule. After the GMP is signed, any work outside the contracted scope must go through the CO process before the contractor proceeds. Change orders are mini-estimates — the same skills used to price the original GMP apply to each CO.
Types of Change Orders
Section titled “Types of Change Orders”| Type | Initiator | Cost Responsibility |
|---|---|---|
| Owner-Directed Change | Owner adds or removes scope | Owner pays (adds to GMP) |
| Constructive Change | Owner action causes cost without formal direction | Owner pays — must be documented |
| Unforeseen Conditions | Site conditions different from contract documents | Owner pays (subject to differing site conditions clause) |
| Design Omissions | Design team missed scope clearly part of project intent | In DB, contractor usually absorbs unless excluded in BOE |
| Design Development | Design evolves from Class 3 to IFC and adds cost | Absorbed by contingency (if within scope) or CO (if new scope) |
| Regulatory / Permit Conditions | AHJ requires more than spec’d | Depends on contract language; typically shared risk |
| Time Extension Only | Schedule impact without cost impact | No GMP change; schedule adjusted |
Step-by-Step Change Order Pricing Process
Section titled “Step-by-Step Change Order Pricing Process”Step 1: Identify and Document
Section titled “Step 1: Identify and Document”- Log in the CO register immediately with CO number, date, and description
- Determine the trigger type
- Do NOT proceed with the work until the CO is formally approved — unless safety requires immediate action (document everything)
Step 2: Scope the Change
Section titled “Step 2: Scope the Change”Write a scope of work for the change:
- What work is being added or deleted?
- Which contract documents establish the change?
- What are the scope boundaries (what’s in, what’s out)?
Step 3: Price the Change
Section titled “Step 3: Price the Change”Method A: Lump Sum — detailed estimate: QTO + sub quotes + direct cost + GC impact + escalation + contingency + fee
Method B: Time and Materials (T&M) — track actual labor hours, materials, equipment daily; apply agreed markups. Use when scope is unknowable in advance or emergency work required before pricing. Always establish T&M rate schedule in the GMP contract upfront.
Method C: Unit Prices — use pre-agreed unit prices from the GMP contract schedule × measured quantity. Good for predictable work types (earthwork CY, concrete CY).
Step 4: Assess Schedule Impact
Section titled “Step 4: Assess Schedule Impact”Every change has a potential schedule impact. Determine:
- Does this change extend the critical path?
- If so, by how many days?
- Cost of schedule extension = extended general conditions per day × days
Even if the CO scope cost is small, a 30-day extension at $4,500/day gen cons = $135,000 in additional cost.
Step 5: Submit and Track
Section titled “Step 5: Submit and Track”Required CO submittal package:
- CO number, project name, date
- Description of change (reference drawing/RFI/direction that triggered it)
- Detailed cost backup (quantities, unit rates, sub quotes)
- Schedule impact analysis
- Total cost request (cost + time)
- Signature block for owner approval
Change Order Register
Section titled “Change Order Register”| CO # | Description | Date Submitted | Amount Requested | Status | Approved Amount | Approved Date |
|---|---|---|---|---|---|---|
| CO-001 | mm/dd | $ | Pending | |||
| CO-002 | mm/dd | $ | Approved | $ | mm/dd |
Constructive Changes — Critical for DB Estimators
Section titled “Constructive Changes — Critical for DB Estimators”A constructive change is a situation where the owner’s actions effectively direct a change without a formal CO. Examples:
- Owner’s design team issues a drawing revision that adds scope
- Owner demands faster schedule — accelerating adds cost
- Owner withholds a decision, causing delay
How to protect yourself:
- Issue a written Notice of Potential Change (NPC) as soon as the event occurs
- Document all impacts in writing (daily reports, emails, meeting minutes)
- Do NOT wait until project completion — most contracts have 30–90 day notice periods after which claims may be waived
Change Order Markups
Section titled “Change Order Markups”| Component | Typical Range |
|---|---|
| Direct labor and material cost | At cost |
| Sub markup (GC overhead on sub work) | 5–10% of sub’s cost |
| Home office overhead | 5–10% of direct cost |
| Profit | 5–10% of direct + overhead |
| Bond (if bonded CO) | Bond rate × CO amount |
Negotiate the CO markup structure into the GMP contract before construction starts — trying to negotiate per-CO creates disputes.
Scenario Example: 35,000 SF Food & Bev Expansion
Section titled “Scenario Example: 35,000 SF Food & Bev Expansion”| CO # | Description | Trigger | Amount | Schedule Impact |
|---|---|---|---|---|
| CO-001 | Owner adds third dock position | Owner-directed | +$87,500 | +14 cal days |
| CO-002 | Existing 6” gas line found 3’ off as-built | Unforeseen | +$31,000 | +7 cal days |
| CO-003 | MEP coordination required FP system redesign | Design coordination | Absorbed in contingency | 0 |
| CO-004 | Owner deletes interior mezzanine (VE) | Owner-directed | -$62,000 | -10 cal days |
| Net Change | +$56,500 | +11 cal days | ||
| Original GMP | $21,400,000 | |||
| Revised GMP | $21,456,500 |
Advisor content
Continue reading with Advisor
This article is part of our Advisor library — written from real projects, not generic explainers.
- Full Support tier vault — equipment, integration, commissioning, takeoff, and more
- Practitioner-level guidance from real projects
- Unlimited AI questions across the Support corpus
$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime
Already subscribed? Sign in