Skip to content
Estimating

Estimate Classification and BOE

Navigation: estimate-classification | index

The AACE Class 1–5 system is the industry standard for calibrating estimate accuracy to design maturity. Every estimate must be classified — this tells the owner and your team exactly how much accuracy to expect.


AACE Class 1–5 — Manufacturing Plant Application

Section titled “AACE Class 1–5 — Manufacturing Plant Application”
ClassDesign CompletenessAccuracy RangeTypical UsePrimary Method
Class 50–2%-50% / +100%Concept screening, portfolio decisionsAnalogous / ROM
Class 41–15%-30% / +50%Study / feasibilityEquipment factored, parametric
Class 310–40%-20% / +30%Budget authorization / GMP candidateSemi-detailed with sub quotes
Class 230–75%-15% / +20%Control estimate / GMP finalizationDetailed with major sub quotes
Class 165–100%-10% / +15%Check estimate / bid/tenderFull bottom-up with all sub bids

Source: AACE RP 18R-97 (Process Industries), RP 17R-97 (General)

Practical rule: Never let an owner treat a Class 3 estimate like a Class 1. Always label estimates with their class and expected accuracy range. The BOE makes this explicit.


FEL StageDescriptionAACE Class
FEL-1Business opportunity / conceptualClass 5
FEL-2Feasibility / preliminary engineeringClass 4
FEL-3Front-End Engineering Design (FEED)Class 3
Detailed DesignConstruction drawingsClass 2 → Class 1

As design matures from Class 5 → Class 1, three things change:

  1. Inputs — from analogous project data to actual vendor quotes and complete drawings
  2. Method — from parametric/factored to full bottom-up quantity takeoff
  3. Contingency — decreases as uncertainty resolves (Class 5: 30–50%; Class 1: 5–10%)

The BOE is the single most important document an estimator produces. It is the narrative that explains, justifies, and bounds every number in the estimate.

The BOE is both a communication tool and a legal document — it often becomes an exhibit to the GMP contract, so scope exclusions and assumptions in the BOE define what the contractor is and is not responsible for.

Required Sections of a Manufacturing Plant BOE

Section titled “Required Sections of a Manufacturing Plant BOE”

Section 1: Project Identification — Name, location, owner, DB firm, revision number, date, prepared by/reviewed by

Section 2: Estimate Classification — AACE Class and accuracy range; percent design completion; drawing list with revision numbers

Section 3: Scope of Work — Inclusions — Explicitly state everything that IS included. Example: “New 40,000 SF production bay addition; two new production lines; utility connections to existing headers; new electrical distribution to production area”

Section 4: Scope of Work — Exclusions — Explicitly state everything NOT included. Common exclusions:

  • Owner-furnished equipment (OFE) and owner-furnished materials
  • Process equipment vendor startup and commissioning labor
  • Production line validation (pharma/food)
  • IT infrastructure, MES/SCADA software
  • Escalation beyond the pricing date

Section 5: Estimating Methodology — For each major cost category, state the method used:

  • “Structural steel — bottom-up QTO from structural drawings; unit rates from RSMeans 2025 Q1 + market check”
  • “Process equipment installation — factored from equipment list at Lang factor of 0.45 of FOB cost”

Section 6: Pricing Basis — Pricing date; location factor applied; labor rates (union vs. open shop; prevailing wage); material pricing source

Section 7: Escalation — Methodology; start/end dates; material vs. labor escalation rates applied separately

Section 8: Contingency — Total amount and %; composition by type (design development, scope gap, execution); flat % vs. probabilistic method

Section 9: Allowances — Specific fixed-dollar allowances for known-but-undefined items (hazmat abatement, permit fees, owner’s T&I)

Section 10: Exclusions and Qualifications — Critical assumptions restated as qualifications:

  • “Estimate assumes soil bearing capacity of 2,000 PSF or better; geotech report not yet received”
  • “Assumes no hazardous materials in existing building”

Before submitting any BOE, verify:

  • Every major cost category has a stated methodology
  • A drawing list (with revision dates) is attached
  • All assumptions and exclusions are written, not implied
  • Contingency basis is documented (not just a percentage)
  • AACE class and accuracy range are clearly labeled
  • Pricing date is explicit

See BOE Template for a ready-to-fill template.

Advisor content

Continue reading with Advisor

This article is part of our Advisor library — written from real projects, not generic explainers.

  • Full Support tier vault — equipment, integration, commissioning, takeoff, and more
  • Practitioner-level guidance from real projects
  • Unlimited AI questions across the Support corpus

$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime