Subcontractor Bidding and Bid Leveling
Navigation: estimating-techniques | index
Sub quotes typically represent 60–80% of total GMP cost on a manufacturing plant project. If you use a sub bid that’s missing scope, you’re carrying a loss. If you use a bid that’s overpriced, you don’t win the job. Bid leveling makes all bids comparable.
Step 1: Write the Scope of Work Package
Section titled “Step 1: Write the Scope of Work Package”Before sending anything to subs, write a clear scope of work for each trade. A weak scope package produces incomplete sub bids that can’t be leveled.
What belongs in a scope package:
- Written scope of work narrative (what is included; what is excluded)
- Drawing list with revision numbers (exactly which drawings to price)
- Applicable specification sections
- Specific inclusions required in the bid:
- Material type and grade
- Labor basis (prevailing wage? union? open shop?)
- Startup and commissioning support hours (specific number, not open-ended)
- As-built drawing preparation
- Warranty terms
- Statement of what the GC will provide (scaffolding, cranes, temporary power)
- Bid date and format instructions
Scope Package by Trade — Manufacturing Plant Expansion
Section titled “Scope Package by Trade — Manufacturing Plant Expansion”| Trade / Division | Items to Specify |
|---|---|
| Site work / Civil (31–33) | Earthwork volume (your estimate), existing utility locations, compaction spec, paving spec |
| Concrete (03) | Slab thickness, rebar spec, flatness F-number spec for industrial floors, vapor barrier |
| Structural Steel (05) | Erection only vs. supply & erect; bolt torque requirements; painting spec |
| Roofing (07) | Membrane type, insulation R-value, warranty year requirement |
| Mechanical / Plumbing (22–23) | Process utilities scope boundary (where does process pipe end and HVAC begin?), equipment connections, test & balance |
| Fire Suppression (21) | System type (wet/dry pipe), hydraulic calc submittal required |
| Electrical (26) | Voltage/phase, equipment connections, MCC supply vs. install, testing |
| Process Equipment Install (40–45) | Vendor-furnished scope, rigging & setting plan, startup support hours |
Step 2: Solicit Bids
Section titled “Step 2: Solicit Bids”- Send invitations via BuildingConnected, SmartBid, or email blast
- Allow minimum 10 working days for mechanical/electrical; 5 days for concrete/steel
- Send a reminder 2 days before due date
- Seek minimum 3 quotes per major scope; settle for 2 if market is tight
Step 3: Receive and Review Bids
Section titled “Step 3: Receive and Review Bids”- Log each bid in your bid tab immediately
- Read the bid letter / cover page carefully before looking at the number
- Note all exclusions, qualifications, and clarifications
- Flag any bids that use different materials or methods (substitutions)
Warning signs in a sub bid:
- Unusually low bid with no exclusions (what did they miss?)
- Long list of exclusions (many items pushed back to GC)
- Unit prices but no lump sum (can’t put in GMP cleanly)
- “Pricing valid for 30 days” — get extensions in writing on long projects
Step 4: Build the Bid Leveling Sheet
Section titled “Step 4: Build the Bid Leveling Sheet”The bid leveling sheet takes every sub bid apart line by line and adjusts each to the same scope basis.
Structure
Section titled “Structure”| Line Item | Your Scope | Sub A | Sub B | Sub C |
|---|---|---|---|---|
| Base bid | — | $A | $B | $C |
| Exclusion: startup hours | Included | Not included | Included | Not included |
| ADD: startup (our est.) | — | +$8,500 | — | +$8,500 |
| Exclusion: permits | Owner provides | $2,200 extra | $2,200 extra | Not included |
| ADD: permits (if applicable) | — | — | — | +$2,200 |
| Leveled Total | $A+8,500 | $B+2,200 | $C+10,700 |
The leveled total is what you use to compare bids — not the base bid number.
Common Scope Gap Items to Check on Every Bid
Section titled “Common Scope Gap Items to Check on Every Bid”- Permits and fees — included or excluded?
- Sales tax on materials (varies by state)
- Startup and commissioning labor hours
- As-built drawings and O&M manuals
- Equipment startup supervision
- Temporary protection (dust walls, temporary HVAC during construction)
- Testing (pressure tests, megger tests, hydrostat tests)
- Warranty — 1 year standard? Callback clause?
- MBE/WBE/DBE requirements if applicable
- Prevailing wage compliance if required
Step 5: Scope Clarification Calls
Section titled “Step 5: Scope Clarification Calls”After leveling, call the 2–3 lowest bidders:
- Confirm their understanding of the scope
- Ask about specific exclusions: “Your bid excludes startup — what would it cost to include?”
- Confirm schedule availability
- Get pricing validity extended in writing if needed
Step 6: Select the Sub and Record the Decision
Section titled “Step 6: Select the Sub and Record the Decision”- Use the leveled total, not the raw bid number
- Consider: schedule availability, bonding capacity, recent project experience, references
- Document selection rationale in the project file
- Never select purely on low price if there are quality or schedule concerns
Step 7: Apply to the Estimate
Section titled “Step 7: Apply to the Estimate”- Enter the leveled sub total under the appropriate CSI division
- Note sub’s name, bid date, and key inclusions/exclusions in estimate notes
- This documentation becomes part of the BOE
Handling Scopes With No Sub Quote
Section titled “Handling Scopes With No Sub Quote”- Estimate using RSMeans unit prices × your quantities (note “unit price estimate, no sub quote” in BOE)
- Add 5–10% scope gap contingency allowance on that scope
- Flag for follow-up sub bidding after award if possible
Trade-Specific Scope Checklists
Section titled “Trade-Specific Scope Checklists”Standard checklist items apply to every trade (see Step 4 above). The following checklists add process trade-specific items commonly missed on manufacturing plant projects.
Mechanical — Process Piping
Section titled “Mechanical — Process Piping”- Pipe material specified (carbon steel, SS 304/316, HDPE, PVC) — not just “process piping”
- Pipe spec (schedule, end connections, fitting standard) included
- Insulation included? Specify type, thickness, cladding material, and who provides jacketing
- Pipe supports — included in mechanical sub or structural sub? Define boundary clearly
- Specialty fittings (strainers, sight glasses, sample points) called out specifically
- Hydrostatic / pressure test included — who provides test water, test pump, isolation blinds?
- Flushing and cleaning after test — included or separate?
- P&ID revision level used to price — document in bid leveling notes
- CIP (Clean-in-Place) piping scope: sanitary fittings (tri-clamp), drainability slope, spray ball connections
- Utility piping (plant air, nitrogen, steam, condensate) — confirm which utilities are in scope
Mechanical — HVAC
Section titled “Mechanical — HVAC”- Process HVAC vs. comfort HVAC — scope boundary defined (who owns the process exhaust and supply for production areas?)
- Make-up air unit (MAU) — included or owner-furnished? If included, equipment furnished by whom?
- Exhaust fans and ductwork for process areas — fume/dust rated vs. standard?
- Test, balance, and commissioning (TAB) — explicitly included; who provides TAB report?
- Controls — BAS/DDC integration by HVAC sub or separate controls sub?
- Kitchen/sanitary exhaust if food processing: Type I/II hood, grease duct, fire suppression
- Freeze protection on refrigerated spaces: heating coils, radiant heat, door heaters
- Energy recovery (ERV/HRV) — if specified, confirm included
Electrical — MCC / Switchgear
Section titled “Electrical — MCC / Switchgear”- MCC furnished by sub or owner-furnished, contractor-installed (OFCI)? Confirm clearly
- Coordination study and arc flash labeling — included or separate?
- Short-circuit and load flow study — who provides? Required before MCC can be labeled
- Conduit and wire to all equipment connections — sub’s scope ends where? At MCC terminals? At equipment junction box?
- Equipment grounds — bonding to structure, grounding electrodes, included?
- Testing and commissioning (megger tests, loop checks) — included; who witnesses?
- Switchgear seismic anchorage if required by jurisdiction or owner spec
- VFD programming and startup support — included for each drive?
- As-built one-line diagrams — included
Electrical — Instrumentation and Controls
Section titled “Electrical — Instrumentation and Controls”- Instrument list revision level used to price
- Field instruments (transmitters, valves, analyzers) — furnished by sub or owner? OFCI?
- Instrument loop drawings (ILDs) / loop tubing — included in scope?
- Control panel fabrication — UL 508A listed panel, sub builds vs. vendor-supplied?
- PLC/SCADA programming — included or separate contract? Define scope of programming (I/O count, screen count)
- Loop checkout and commissioning hours — specify per loop or lump sum
- Calibration of instruments — included? Traceability documentation required?
Industrial Refrigeration (Ammonia — PSM Facilities)
Section titled “Industrial Refrigeration (Ammonia — PSM Facilities)”[!warning] PSM scope — additional diligence required Ammonia refrigeration systems with >10,000 lb charge are subject to OSHA PSM (29 CFR 1910.119). Confirm sub has PSM-competent engineering resources and refrigeration mechanic crew.
- PSM compliance documentation — PHA (Process Hazard Analysis), P&IDs, operating procedures — included in sub scope or separate?
- IIAR (International Institute of Ammonia Refrigeration) standards compliance confirmed (IIAR 2, IIAR 5)
- Pressure vessel certification (ASME VIII stamps on vessels and receivers)
- Relief valve sizing and discharge piping per IIAR 2 Section 13
- Leak detection system (ammonia detectors, alarm panel) — included?
- Engine room ventilation — IIAR minimum 0.5 CFM/SF or 30 air changes/hour, whichever is greater; confirm design included
- Emergency pressure control system (high-pressure safety cutouts) — included
- Refrigerant charge quantity and initial fill — included in contract value?
- Startup and commissioning support — defined in hours; IIAR 5 Section 5 startup checklist compliance
CIP / Sanitary Piping (Food & Beverage)
Section titled “CIP / Sanitary Piping (Food & Beverage)”- Sanitary fitting standard specified (3-A, ASME BPE, DIN 11851) — confirm sub’s experience with required standard
- Welder qualifications — ASME BPE or 3-A weld documentation required?
- Weld inspection: borescope inspection of interior welds specified? Who provides report?
- Drainability slope (minimum 1/8” per foot toward drain points) — sub confirms in layout review?
- Dead leg elimination — maximum dead leg length per owner’s SOP or FDA guidance (typically <2× pipe diameter)
- CIP supply/return routing — confirm flow velocities designed for turbulent cleaning (>5 ft/sec)
- Surface finish (Ra) of interior welds — specified (typically 32–63 µin Ra for product contact)
- Passivation after installation — included? Who provides certification documentation?
- Pressure test (water) before passivation — included with documentation
Advisor content
Continue reading with Advisor
This article is part of our Advisor library — written from real projects, not generic explainers.
- Full Support tier vault — equipment, integration, commissioning, takeoff, and more
- Practitioner-level guidance from real projects
- Unlimited AI questions across the Support corpus
$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime
Already subscribed? Sign in