Owner Project Costs
Navigation: estimating-techniques | index
The GC’s GMP covers construction cost — what it takes to build the facility. The owner’s total capital investment includes a second category of costs that never appear in the GMP: design fees if not sub’d to the GC, land, owner’s project team, regulatory compliance, technology, equipment the GC doesn’t install, and startup. These are Owner Project Costs (OPC).
On a well-run capital project, OPC is scoped and budgeted at FEL-1 alongside TIC. On a poorly run one, it surfaces as a series of late surprises after the GMP is signed.
TIC is what the contractor delivers. TIC + OPC is what the owner spends. The difference commonly runs 20–40% of TIC. Budget both from the start.
Total Project Investment Framework
Section titled “Total Project Investment Framework”Total Project Investment ├── TIC (Total Installed Cost) │ └── What the GC's GMP covers (see [Pricing and Cost Assembly](./pricing-and-cost-assembly)) ├── Owner Project Costs (OPC) │ ├── Pre-construction costs │ ├── Owner's project team │ ├── Design (if not in GMP) │ ├── Owner-furnished equipment (OFOI) │ ├── Technology and systems │ ├── Regulatory and compliance │ ├── Commissioning and startup │ └── Post-construction costs └── Total Project InvestmentOPC Categories — Detailed Breakdown
Section titled “OPC Categories — Detailed Breakdown”Pre-Construction
Section titled “Pre-Construction”| Item | Description | Typical Cost Range |
|---|---|---|
| Land acquisition | Purchase price + closing costs + transfer taxes | Market-driven |
| Environmental assessment | Phase I ESA ($3,000–$6,000); Phase II if needed ($15,000–$80,000) | $3,000–$80,000 |
| Geotechnical investigation | Borings, lab testing, report | $15,000–$60,000 |
| Site survey and title | ALTA survey, boundary survey | $5,000–$25,000 |
| Utility availability studies | Power, gas, water, sewer capacity confirmation from utilities | $5,000–$30,000 |
| Feasibility studies | Traffic, environmental, market | $20,000–$150,000 |
| Incentive / economic development | Legal fees, application prep for tax abatements, TIF, grants | $10,000–$75,000 |
| Zoning and entitlements | Attorney fees, filing fees, public hearings | $10,000–$100,000 |
Design Fees (if not subcontracted to GC)
Section titled “Design Fees (if not subcontracted to GC)”In design-bid-build or when the owner retains their own A/E firm, design fees are an OPC:
| Service | Typical Fee (% of construction cost) |
|---|---|
| Architecture + engineering (full services) | 5–12% |
| Process engineering only | 2–5% |
| Civil / site engineering only | 1–3% |
| Specialty consulting (food safety, structural peer review) | 0.5–2% |
In design-build, the A/E is typically a sub to the GC and the design fee is in the GMP. Confirm this explicitly — it is the most common source of confusion in D-B OPC accounting.
Owner’s Project Team
Section titled “Owner’s Project Team”Every capital project requires owner staff or consultants to manage it. These costs are real and should be in the budget.
| Role | Typical Cost Basis |
|---|---|
| Owner’s Project Manager | Salary + benefits for duration; or $100–$250/hr for contract PM |
| Owner’s Construction Representative (field) | Salary or $75–$175/hr |
| Food safety / QA lead (for F&B, CPG, pharma) | Salary or $85–$175/hr |
| Procurement manager (for OFOI equipment) | Salary or $85–$150/hr |
| IT/OT integration lead | $100–$200/hr for specialist |
| Legal (contract review, change order disputes) | $250–$500/hr |
Rule of thumb: Owner’s project team costs run 2–5% of TIC on a well-staffed capital project. Understaffing the owner’s team is a leading cause of scope growth and change orders — the owner can’t make decisions fast enough, and the contractor waits.
Owner-Furnished Equipment (OFOI)
Section titled “Owner-Furnished Equipment (OFOI)”Equipment the owner purchases and has installed by their own forces or OEM:
| Item | Notes |
|---|---|
| Production equipment (OFOI) | Owner contracts directly with OEM; GC only prepares space (pads, rough-ins) |
| Specialty process equipment | Vendor-supplied with proprietary installation team |
| IT/OT servers and networking | Owner’s IT contracts separately |
| Security systems (CCTV, access control) | Frequently owner-furnished even if GC installs conduit |
| Lab equipment | Always owner-purchased; GC provides lab casework and utilities only |
OFOI equipment cost is entirely outside the GMP. Always document the scope split at FEL-2 to avoid double-counting or gaps.
Technology and Systems
Section titled “Technology and Systems”| System | Description | Typical Cost Range | |---|---| | Manufacturing Execution System (MES) | Production scheduling, tracking, quality management integration | $200,000–$2,000,000+ | | Plant historian / SCADA | Real-time data collection from PLCs and sensors | $50,000–$500,000 | | ERP integration | SAP, Oracle, or similar; interface to shop floor | $100,000–$1,000,000 (project-specific) | | LIMS (Laboratory Information Management) | For QC labs | $50,000–$300,000 | | Network infrastructure | Switches, cabling, wireless APs, cybersecurity | $0.50–$3.00/SF of facility | | Physical security (cameras, access control) | $2.00–$6.00/SF |
Technology costs are frequently omitted from early-stage project budgets because they are managed by IT departments separate from capital projects. Include them or flag the exclusion explicitly.
Regulatory and Compliance Costs
Section titled “Regulatory and Compliance Costs”| Item | Description | Cost Range | |---|---| | Permitting fees | Building permit, fire, mechanical, electrical, plumbing | 0.5–1.5% of construction cost (jurisdiction-dependent) | | Plan review fees | Separate from permit fees in some jurisdictions | $5,000–$50,000 | | Third-party special inspections | Concrete, steel, soils — required by IBC for many project types | $20,000–$100,000 | | Commissioning agent (third-party) | Independent verification of systems | 0.5–2% of MEP cost | | Factory acceptance testing (FAT) | Travel to vendor site; per diem; testing labor | $5,000–$50,000 per major equipment item |
Furniture, Fixtures, and Equipment (FF&E)
Section titled “Furniture, Fixtures, and Equipment (FF&E)”Office and non-production facility items typically excluded from construction GMP:
- Office furniture, workstations, lockers
- Break room equipment (refrigerators, microwaves, vending)
- Safety equipment (fire extinguishers, AEDs, first aid stations)
- Signage and graphics
Rule of thumb: $10–$30/SF of office and support space for FF&E.
Financing Costs
Section titled “Financing Costs”For owner-financed projects (construction loan):
- Construction loan interest: Balance × interest rate × construction duration. On a $20M project at 7.5% over 18 months: ~$1,900,000 in interest carry
- Loan origination and fees: 0.5–2% of loan amount
- Owner’s insurance during construction: Builder’s risk is typically GC-provided (in GMP); owner may carry additional coverage
F&B and CPG — Owner Project Costs
Section titled “F&B and CPG — Owner Project Costs”F&B and CPG projects have specific OPC categories that are frequently omitted from early budgets.
Regulatory and Food Safety OPC
Section titled “Regulatory and Food Safety OPC”| Item | Timing | Cost Range |
|---|---|---|
| USDA FSIS pre-operational review | Pre-opening | $5,000–$25,000 owner prep cost |
| FDA facility registration | Pre-first-shipment | Minimal; administrative only |
| FSMA Preventive Controls consultant | Pre-opening to implement HARPC/HACCP | $15,000–$50,000 |
| Third-party food safety certification (SQF, BRC, FSSC 22000) | Within 60–90 days of opening | $5,000–$20,000 initial; annual thereafter |
| Environmental monitoring program setup | Pre-opening | $5,000–$15,000 in lab contracts and equipment |
| Wastewater permit (if pre-treatment required) | Pre-construction through opening | $5,000–$50,000 |
Production and Startup OPC
Section titled “Production and Startup OPC”| Item | Description | Cost Range |
|---|---|---|
| CIP commissioning specialist | Verify CIP circuits, flow velocities, temperatures | $10,000–$40,000 |
| Temperature mapping | Refrigerated/frozen spaces before first food storage | $5,000–$25,000 per space |
| Compressed air food-grade testing | ISO 8573-1 verification | $2,000–$8,000 |
| Startup product waste | Product destroyed or held during first production runs | 2–5 production days of output value |
| Trial production runs | Staffing, utilities, consumables for pre-production runs | $20,000–$200,000 |
| Operator hiring and training lead time | Operators hired and trained before production; no revenue | 4–12 weeks of labor cost |
Technology OPC Specific to F&B/CPG
Section titled “Technology OPC Specific to F&B/CPG”| System | Notes |
|---|---|
| Traceability system | Lot tracking from raw material to finished goods; FDA/FSMA requirement |
| Label compliance software | Nutritional data, allergen labeling, regulatory label review |
| HACCP/food safety documentation software | Recipe management, HACCP records, audit trails |
| Cold chain monitoring | Real-time temperature monitoring with alert/logging for FDA compliance |
| ERP / production planning integration | SAP, Oracle, or mid-market ERP for production scheduling and inventory |
Assembling the Total Project Investment Budget
Section titled “Assembling the Total Project Investment Budget”Present to the owner at FEL-1 with explicit uncertainty ranges. Do not combine TIC and OPC into a single number — keep them as separate line items so the owner understands what they are buying:
FEL-1 Total Project Investment — [Project Name]Pricing date: Q[N] YYYY | Estimate class: Class 5
TIC (Construction) $XX,000,000 (−30% / +50% accuracy) └── Escalation allowance included
Owner Project Costs (OPC): Pre-construction / land $X,000,000 Design fees (if owner-retained) $X,000,000 Owner project team $X,000,000 OFOI equipment $X,000,000 ← confirm scope split Technology / IT $X,000,000 Regulatory / compliance $X,000,000 Commissioning and startup $X,000,000 FF&E $X,000,000 Financing costs $X,000,000 OPC Subtotal $XX,000,000
Owner Contingency (management reserve) $X,000,000 (separate from GMP contingency)
TOTAL PROJECT INVESTMENT $XX,000,000OPC as % of TIC (industry benchmarks):
| Project Type | OPC as % of TIC |
|---|---|
| Basic light industrial | 10–18% |
| CPG / food processing | 18–28% |
| Food processing with significant OFOI equipment | 25–40% |
| Highly regulated (pharma, sterile food) | 30–50%+ |
Common OPC Omissions to Flag at Every FEL Review
Section titled “Common OPC Omissions to Flag at Every FEL Review”At each phase gate, check whether these items are in the budget:
- Owner’s project management team cost (duration × loaded rate)
- Technology/IT systems explicitly scoped or explicitly excluded
- OFOI equipment list confirmed and priced (or excluded with owner acknowledgment)
- Regulatory filing fees and compliance consultant for this specific facility type
- Commissioning and startup budget as a named line item
- Startup product waste budget (for process manufacturing)
- Training cost for new operations staff before first production
- Financing cost if project is debt-financed
Related Pages
Section titled “Related Pages”- Pricing and Cost Assembly — the GMP side of total project investment
- Commissioning and Startup — startup costs that are the largest OPC variable
- Closeout and Lessons Learned — OPC actuals feed the historical cost library
- GMP Contingency Structure — owner contingency (management reserve) lives here
- Food and Beverage — F&B regulatory OPC
- Light Industrial and CPG — CPG scope split and OFOI documentation
Navigation: estimating-techniques | index
Advisor content
Continue reading with Advisor
This article is part of our Advisor library — written from real projects, not generic explainers.
- Full Support tier vault — equipment, integration, commissioning, takeoff, and more
- Practitioner-level guidance from real projects
- Unlimited AI questions across the Support corpus
$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime
Already subscribed? Sign in