Delivery Methods and Contracts
Navigation: delivery-contracts | index
Understanding delivery method is critical because it determines who holds design risk, how estimates are used, and what your contractual obligations are.
The Four Major Delivery Models
Section titled “The Four Major Delivery Models”| Method | Who Designs | Who Builds | Price Format | Estimator’s Role |
|---|---|---|---|---|
| Design-Bid-Build (DBB) | Owner’s A/E firm | Separate GC (low bid) | Lump sum or unit price | GC prices completed drawings; limited design input |
| Design-Build (DB) | DB firm (in-house or sub’d A/E) | Same DB firm | GMP or lump sum | Estimator prices evolving design; collaborates with design team |
| Construction Manager at Risk (CMAR) | Owner’s A/E firm | CM/GC at risk | GMP | Estimator provides cost guidance during design; GMP set at defined milestone |
| EPC (Engineering, Procurement, Construction) | EPC contractor | EPC contractor | Lump sum or reimbursable | Full turnkey; estimator responsible for engineering, procurement, and construction costs |
The Guaranteed Maximum Price (GMP)
Section titled “The Guaranteed Maximum Price (GMP)”The GMP is the absolute ceiling the contractor commits to for total project cost.
What the GMP Covers
Section titled “What the GMP Covers”GMP = Cost of Work + General Conditions + Design Fee + Contractor Fee + Contingency + Allowances- Cost of Work — direct labor, materials, equipment, subcontractor costs
- General Conditions — field supervision, temporary facilities, site safety, project management
- Design Fees — if the A/E is a sub to the DB firm
- Contractor Fee — overhead and profit
- Allowances — defined quantities for items not yet fully designed
- Contingency — contractor-held reserve for scope gaps and risk events
Shared Savings
Section titled “Shared Savings”If final project cost comes in below the GMP, the contract typically specifies a split (e.g., owner 75% / contractor 25%). This motivates the contractor to manage costs efficiently.
Who Bears Overruns
Section titled “Who Bears Overruns”If costs exceed the GMP due to contractor-driven causes, the contractor absorbs the overage. The contractor is protected only if:
- The owner directs a change in scope
- Unforeseen conditions are discovered (subject to contract language)
- Owner-caused delays add cost
When Is the GMP Set?
Section titled “When Is the GMP Set?”Most commonly at approximately 30–60% design completion (end of FEED or schematic design). The earlier it is set, the more contingency is required to cover design development risk.
Contract Risk Matrix: Owner vs. Contractor
Section titled “Contract Risk Matrix: Owner vs. Contractor”| Risk Category | DBB | DB/GMP | EPC Lump Sum |
|---|---|---|---|
| Design completeness at bid | Owner | Contractor | Contractor |
| Scope interpretation errors | Contractor | Contractor | Contractor |
| Unforeseen site conditions | Contractor (with DSC clause) | Negotiated | Usually contractor |
| Price escalation (materials) | Contractor | Contractor (unless clause) | Contractor |
| Schedule-driven cost growth | Contractor | Shared — depends on cause | Contractor |
| Owner-directed scope changes | Change order | Change order to GMP | Change order |
Key implication: In design-build, the contractor takes on design risk that doesn’t exist in DBB. The estimator must price scope gaps, design development cost, and specification uncertainties — not just what the drawings show.
Design-Build Delivery Steps (Estimator’s View)
Section titled “Design-Build Delivery Steps (Estimator’s View)”- Site Selection / Program Definition — Owner defines facility requirements, capacity targets, site. Estimator may provide ROM cost guidance.
- RFQ Issuance — Owner pre-qualifies DB firms. Estimator helps write the firm’s qualifications.
- RFP Issuance — Owner issues RFP with performance specs and program. Estimator receives and reviews all documents.
- Proposal Preparation — Estimator develops the cost proposal (typically Class 4 or 3) for the technical proposal.
- Award / Kickoff — DB contract awarded. Estimator transitions to preconstruction estimating.
- Design Development — Estimator tracks cost in real time as design evolves; issues design alternatives for VE decisions.
- GMP Development — Estimator prepares the definitive GMP estimate (Class 2 or 1), compiles BOE, and presents for owner approval.
- Construction and Closeout — Estimator supports change order pricing, EVM reporting, and final cost reconciliation.
Open Book Policy
Section titled “Open Book Policy”Many DB/GMP contracts require the owner to have audit rights over actual cost records. The estimator must ensure:
- All cost categories match the Schedule of Values (SOV)
- Sub buyouts and trade contract awards are documented
- Contingency draws are logged and justified
- Nothing is billed as “cost of work” that is actually contractor overhead
Relevant Contract Forms
Section titled “Relevant Contract Forms”| Contract Form | Issuer | Use Case |
|---|---|---|
| ConsensusDocs 410 / 410.1 | ConsensusDocs Coalition | Design-build; GMP provisions |
| AIA A141 | American Institute of Architects | Design-build; owner-contractor |
| DBIA Standard Form | Design-Build Institute of America | DB-specific; balanced risk allocation |
| AGC 415 | Associated General Contractors | CM at Risk with GMP |
Advisor content
Continue reading with Advisor
This article is part of our Advisor library — written from real projects, not generic explainers.
- Full Support tier vault — equipment, integration, commissioning, takeoff, and more
- Practitioner-level guidance from real projects
- Unlimited AI questions across the Support corpus
$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime
Already subscribed? Sign in