Skip to content
Estimating

Delivery Methods and Contracts

Navigation: delivery-contracts | index

Understanding delivery method is critical because it determines who holds design risk, how estimates are used, and what your contractual obligations are.


MethodWho DesignsWho BuildsPrice FormatEstimator’s Role
Design-Bid-Build (DBB)Owner’s A/E firmSeparate GC (low bid)Lump sum or unit priceGC prices completed drawings; limited design input
Design-Build (DB)DB firm (in-house or sub’d A/E)Same DB firmGMP or lump sumEstimator prices evolving design; collaborates with design team
Construction Manager at Risk (CMAR)Owner’s A/E firmCM/GC at riskGMPEstimator provides cost guidance during design; GMP set at defined milestone
EPC (Engineering, Procurement, Construction)EPC contractorEPC contractorLump sum or reimbursableFull turnkey; estimator responsible for engineering, procurement, and construction costs

The GMP is the absolute ceiling the contractor commits to for total project cost.

GMP = Cost of Work + General Conditions + Design Fee + Contractor Fee + Contingency + Allowances
  • Cost of Work — direct labor, materials, equipment, subcontractor costs
  • General Conditions — field supervision, temporary facilities, site safety, project management
  • Design Fees — if the A/E is a sub to the DB firm
  • Contractor Fee — overhead and profit
  • Allowances — defined quantities for items not yet fully designed
  • Contingency — contractor-held reserve for scope gaps and risk events

If final project cost comes in below the GMP, the contract typically specifies a split (e.g., owner 75% / contractor 25%). This motivates the contractor to manage costs efficiently.

If costs exceed the GMP due to contractor-driven causes, the contractor absorbs the overage. The contractor is protected only if:

  • The owner directs a change in scope
  • Unforeseen conditions are discovered (subject to contract language)
  • Owner-caused delays add cost

Most commonly at approximately 30–60% design completion (end of FEED or schematic design). The earlier it is set, the more contingency is required to cover design development risk.


Contract Risk Matrix: Owner vs. Contractor

Section titled “Contract Risk Matrix: Owner vs. Contractor”
Risk CategoryDBBDB/GMPEPC Lump Sum
Design completeness at bidOwnerContractorContractor
Scope interpretation errorsContractorContractorContractor
Unforeseen site conditionsContractor (with DSC clause)NegotiatedUsually contractor
Price escalation (materials)ContractorContractor (unless clause)Contractor
Schedule-driven cost growthContractorShared — depends on causeContractor
Owner-directed scope changesChange orderChange order to GMPChange order

Key implication: In design-build, the contractor takes on design risk that doesn’t exist in DBB. The estimator must price scope gaps, design development cost, and specification uncertainties — not just what the drawings show.


Design-Build Delivery Steps (Estimator’s View)

Section titled “Design-Build Delivery Steps (Estimator’s View)”
  1. Site Selection / Program Definition — Owner defines facility requirements, capacity targets, site. Estimator may provide ROM cost guidance.
  2. RFQ Issuance — Owner pre-qualifies DB firms. Estimator helps write the firm’s qualifications.
  3. RFP Issuance — Owner issues RFP with performance specs and program. Estimator receives and reviews all documents.
  4. Proposal Preparation — Estimator develops the cost proposal (typically Class 4 or 3) for the technical proposal.
  5. Award / Kickoff — DB contract awarded. Estimator transitions to preconstruction estimating.
  6. Design Development — Estimator tracks cost in real time as design evolves; issues design alternatives for VE decisions.
  7. GMP Development — Estimator prepares the definitive GMP estimate (Class 2 or 1), compiles BOE, and presents for owner approval.
  8. Construction and Closeout — Estimator supports change order pricing, EVM reporting, and final cost reconciliation.

Many DB/GMP contracts require the owner to have audit rights over actual cost records. The estimator must ensure:

  • All cost categories match the Schedule of Values (SOV)
  • Sub buyouts and trade contract awards are documented
  • Contingency draws are logged and justified
  • Nothing is billed as “cost of work” that is actually contractor overhead

Contract FormIssuerUse Case
ConsensusDocs 410 / 410.1ConsensusDocs CoalitionDesign-build; GMP provisions
AIA A141American Institute of ArchitectsDesign-build; owner-contractor
DBIA Standard FormDesign-Build Institute of AmericaDB-specific; balanced risk allocation
AGC 415Associated General ContractorsCM at Risk with GMP

Advisor content

Continue reading with Advisor

This article is part of our Advisor library — written from real projects, not generic explainers.

  • Full Support tier vault — equipment, integration, commissioning, takeoff, and more
  • Practitioner-level guidance from real projects
  • Unlimited AI questions across the Support corpus

$19/mo Support · $49/mo Advisor · $99/mo Principal · cancel anytime